San Ramon Valley Boulevard Widening (Phase 1)

Southwest County
PROJECT BUDGET $8.8 Million
PROJECT SPONSOR
San Ramon
LOCATION:
San Ramon Valley Boulevard in San Ramon
STATUS:
Completed
Under
Phase two of this project will move overhead utilities underground.

This project widens San Ramon Valley Boulevard between Alcosta Boulevard and Montevideo Drive. The project was constructed in two phases. The first phase includes widening of the roadway from two to four lanes at the extreme north and south ends of the project, and realignment of the roadway and utility undergrounding at the south end. Other work included interim relocation of overhead utilities along the middle section of the project, installation of a traffic signal at Pine Valley Road, and construction of medians, turn pockets and landscaping throughout. Adjacent developers constructed c ...more